Connection to a Newly Constructed Building or Plant

Connection to a Newly Constructed Building or Plant
1. Who, why and where can apply for the connection? What are the required documents?

Real or legal person who would like to supply electrical power by connection to the distribution system for a new plant or place of utilization applies directly to the Regional Offices with a petition

If the property has been rented, on condition that the property owner and/or owners or their agents submit a written statement;

The real or legal person who would like to supply the electrical power by connecting to the distribution system for a limited period of time for purpose of utilization apply on condition that they submit the electrical power project and the permission document which is required for the purpose of utilization together with the following documents:

a) The land registration, the electrical power project that is approved by the Municipality and the Building Audit Establishment,

b) For those which are within public improvement area, the occupancy per Articles 30 and 31 of the Public Improvement Law numbered 3194,

c) For those who are within and around arable fields and settlement areas of villages, the occupancy per Articles 27 and 30 of the Public Improvement Law numbered 3194,

d) For those which are outside the public improvement and settlement areas of villages, the letter which shall be granted by the Provincial Directorates of Environment and Urbanization for occupancy permit,

e) For areas of utilization which do not require license, the letter of permit which shall be granted by the relevant authorities within the scope of the regulation,

f) And the other documents which shall be requested if the relevant regulation requires so.

2. How does the evaluation period of the application evolve? How is the connection agreement made?

It is a principle that the request of real or legal persons for connection to the distribution system is met by the legal person who holds the distribution license within the framework of the provisions of the relevant regulation and service is provided through connection agreement.

The application that is made for the connection is evaluated by the legal person who holds the distribution license also considering the points such as investment of extension within the framework of the current status of the distribution system or a new investment which is required.

If the request for the connection of the current status of the distribution is deemed appropriate, connection agreement is entered into between our company and the applicant.

The connection fee is charged and collected for once only when the first connection agreement is being made and it is not returned. (Year of 2015 Current; 0-15 kW (inclusive) is 69.8 TL and over 15-100 kW 159.6 TL, 100 kW is 202.8 TL; O.G costs, 0-400 kVA (inclusive) is 660.8 TL, over 400 kVA is 821.2 TL (The decision of The Energy Market Regulatory Authority dated December 04, 2014 and numbered 5335-2 which was published in the official gazette dated December 13, 2014 and numbered 29240)

As long as the place of utilization that is in the address which is indicated in the connection agreement exists, the connection agreement remains in force and a new connection agreement is not required in case of customer change in the place of utilization in question.

3. When and how is the system connection established?

The retail sales agreement or the mutual agreement has to be submitted to the relevant person in order for the connection of the real or the legal person who has entered into the connection agreement is connected to the distribution system as customer.

Before the connection to the system is established, the compatibility of the measurement devices and circuits of the customer are checked by the legal person who holds the distribution license and the relevant sections of the meter and measurement circuits are sealed, meter is read and a minute is drawn up with regard to the first index value which is detected and connection to the system

a) Within three working days in the public improvement area,

b) Within five working days outside the public improvement area.


4. In which cases should I make a new connection?

All the applications which require a new subscription number and the cases which require change of connection point due to reasons such as increased power require a new application. The cases such as change of name, title are not within the scope of a new application.

5. Is a new connection required in urban transformation?

The urban transformation cannot take place over the current connection. It requires a new connection agreement to be made. The old agreement must be terminated before the building is demolished.

6. What are the required operations in case of change in power of connection?

The customers who are not residence subscribers apply Regional Offices within seven working days together with the modification project if the connection power that is in the plants which belong to them is increased by more than twenty percent.

The legal person who holds the distribution license examines the modification project and notifies their answer, which will constitute a basis for the implementation, to the customer in written format within fifteen days together with the results of the examination.

If a cost is incurred due to increase in connection power, operation is carried out within the framework of Article 36 of the Regulation on Customer Services on the Electricity Market and the costs which are related to the operation that has been carried out are collected from the customer. The connection agreement is modified so that it contains the actions that have been taken.

The provisions of the Clause f of the Article 32 of the Regulation on Customer Services on the Electricity Market is applicable for the customers who do not fulfill such responsibility with regard to the illegal consumption of electrical power.

7. What are the documents that are required for the temporary acceptance of electrical power distribution plants?
  • Petition for requesting temporary/final acceptance (applicant)
  • The minute which indicates readiness for temporary/final acceptance (applicant and the relevant regional directorate jointly)
  • The approved project of the plant (justification report, layout plan, ENH profile, transformer settlement plan, AG-OG single-line diagram of transformer, identification of transformer power, short circuit calculation, compensation calculation, grounding calculation) (applicant or the relevant regional directorate)
  • Letter of energy permission (applicant or the relevant regional directorate)
  • The letter of attorney or the agreement that is submitted by the owner of the plant to the contractor (applicant)
  • The letter of authorization by the contractor for the responsible electrical engineer who will take part in the temporary acceptance or the letter of attorney which has been granted by the contractor to the responsible electricity who does not work under  the contractor but who will take part in the temporary acceptance (applicant)
  • The letter of authorization for the person who is authorized by the plant owner if they shall not take part in the acceptance (applicant)
  • Bill of quantities and its cost (applicant)
  • Tax certificate (applicant)
  • Address information (applicant)
  • Type and routine and test reports for the materials that are used in the plant (transformer, cell, mansion etc.) (applicant)
  • Grounding resistance/lighting/relay/meter controls and minute (applicant or the relevant regional directorate)
  • Other works that are requested be done for energy permit (applicant or the relevant regional directorate)
  • The photographs of the plant (on electronic medium) (applicant)
  • The name and title of the technical personnel who will take part in the commission (OSB/Distribution company’s personnel) (the relevant regional directorate)
  • SMM document (applicant)
  • Approved Justification Report (applicant or the relevant regional directorate)
  • Transfer of Location, Construction Acceptance, Location Detection Report (applicant and/or the Real Estate Expropriation Directorate of Our Company)
  • Cost of Temporary/Final Acceptance (applicant)

The above documents and information must be submitted with regard to the execution of temporary/final acceptance operations of the electrical power plants, the constructions of which are completed by third persons, establishments or institutions, by our Company or TEDAŞ Boğaziçi Regional Coordinator.

8. The Operations which are related to the take-over of electrical distribution plants in case of joint utilization

The distribution plants which are used by one or more consumers are taken over by our company within the framework of the process that is foreseen in the investment plan in line with the procedures and principles that are determined by the Authority per Article 37 of the Regulation on Connection and System Utilization on the Electricity Market . If the owner or owners of the plants which shall be used jointly do not give consent, they are expropriated.

The procedures and principles which are related to the take-over are drawn up by the institution. The documents which shall be required for take-over operations are as follows:

  • Application petition if the applicant places the request (applicant)
  • Signatory circular (original or notary-approved) (applicant)
  • Letter of authorization (for legal persons) (original or notary-approved) (applicant)
  • Letter of attorney and the agreement which indicate that the owners of the line agree to transfer of the plant (notary approved) (original) (applicant)
  • Certificate of tax liability or tax certificate
  • The document which shows the IBAN number
  • Project of the electrical power distribution plant which constitutes the subject of the take-over (applicant)
  • Temporary acceptance minute of the electrical power distribution plant which constitutes the subject of the take-over (applicant)
  • The cover letter which contains the names and subscription numbers of the owners of lines (the relevant regional directorate)
  • The agreement minute which is signed by the parties (applicant and the relevant regional directorate jointly)
  • Calculation sheet (the members of our company’s commission)
  • The mapping of the operations with regard to the transfer and the letter of examination in terms of ownership (the Real Estate Expropriation Directorate of Our Company)
  • Single Line Diagram (the relevant regional directorate)

9.  What is short-term subscription? In which cases can it be done?

Electrical power is supplied to real and legal persons who request it for short-term works due to compulsory reasons (movie set, welding, grinding etc.) for 1 (one) month at most and in a way that it can be extended for 1 (one) more month at most, if required, by instituting a meter and measuring depending on the opinion of the distribution company with regard to compatibility or without measuring based on the consumption which shall be calculated over the installed power values and the cost which is calculated over business tariffs (the link to such tariffs, if determined, must be provided) is collected in advance against the bill.